Hesketh Crescent Play Area Update

Unfortunately, the dates have been pushed back for the work on the new Hesketh Crescent play area. The implication of this is that the contract will not be completed this winter as originally planned, but in February next year.

Unfortunately, the dates have been pushed back for the work on the new Hesketh Crescent play area.

The revised the tender/contract dates are as follows:

  • Invitation to tender : 9 September
  • Tender return date : 30 September (3 week tender period)
  • Appointment of contractor: 7 October
  • Indicative start date: 4 November  (4 week contract preparation/site mobilisation period)
  • Indicative practical completion: 9 February  2016 (10 week contract period, allowing for Christmas holidays)

The implication of this is that the contract will not be completed this winter as originally planned, but in February next year.

I realise that this is disappointing news, but it is definitely going ahead.

Please don't hesitate to contact me if you have any further questions on this or any other matter.